ZT42 - No Objection Certificate (Infrastructure)

Prev Next

A No Objection Certificate is a formal document issued by the municipality confirming that a proposed project, development, or activity has been assessed for its potential impact on the ROW and existing and planned public infrastructure, transportation networks, and utilities, and that no objection exists to the proposal proceeding under the specified drawings, conditions and regulatory requirements.

This service allows the applicant to request the issuance of various infrastructure NOC types (Utility Networks and House Connections, Roads, Development Projects, and Hydrology) across a variety of stages (Pre-concept / Concept, Design, Design Modification, Construction, Renewal, Maintenance, Completion, and Temporary and Permanent Permits.)

The NOC type and stage differ in the required documents as detailed and outlined in the Infrastructure NOC Submission Guidelines.

Eligible Applicants:

Governmental entities, Developers, Consultants and Contractors


How Long Will It Take? The application review and processing timeline varies based on the specific request subtype as shown in the table below.

#

Application Type

Application Sub-type

Application Processing Time

1

Utility

House Connection - Electricity LV Cables

10

2

Utility

House Connection - Electricity HV Cables

10

3

Utility

House Connection - Water

10

4

Utility

House Connection - Telecommunication

10

5

Utility

House Connection - Sewerage

10

6

Utility

Network Services Project

20

7

Utility

Network Service - Electricity (MV/HV) Underground

20

8

Utility

Network Service - Electricity (MV/HV) Overhead

20

9

Utility

Network Service - Water

20

10

Utility

Network Service - Storm Water Drainage

30

11

Utility

Network Service - Sewerage

30

12

Utility

Network Service - Irrigation

20

13

Utility

Network Service - Gas/Fuel

20

14

Utility

Network Service - Telecommunication

20

15

Utility

Network Service - Firefighting (Civil Defense)

20

16

Roads

Roads Project

30

17

Roads

Access roads (Entry & Exit)

20

18

Roads

Parking

10

19

Hydrology

Integrated hydrology project

30

20

Hydrology

Storage Structure (Dam/Pond)

30

21

Hydrology

Crossing Structure (Culvert/Irish crossing)

30

22

Hydrology

Diversion Structure (Channel/Ditch/Dike)

30

23

Development Project

Development Project

30

24

Temporary Permits

Trial Trenches NOC

5

25

Temporary Permits

Geotechnical investigation Report

5

26

Temporary Permits

Wells approval

5

27

Temporary Permits

Temporary road diversions/Lane Closures/Project access

20

28

Temporary Permits

Temporary project sign

10

29

Temporary Permits

Dewatering and discharge

5

30

Permanent Permits

Traffic Calming Devices

10

31

Permanent Permits

Pedestrian & Cycling Facilities

10

32

Permanent Permits

Directional Traffic Signs

10

33

Permanent Permits

Supplemental guide signs

10

34

Permanent Permits

Advertisement signs

10

What Will You Get?

Approval Output:

-No Objection Certificate (NOC).

-Approved drawings PDF & CAD.

Rejection Output:

-Comments Register / Rejection reasons.

How Do You Apply?

1-You can apply for this service online through https://rakdigital.rak.ae by using your UAE Pass and selecting “No Objection Certificate (Infrastructure Works)” to begin your application.

2. Fill in the submission form: Select the correct NOC stage, type and sub-type, add any applicable comments, fill the details and upload all required documents.

3.Await the review and assessment of your application by the Infrastructure Permitting Section.

4. The application will proceed upon successful verification of the submitted information. Applications containing insufficient information will be rejected.

5. You may receive a request for additional information via email or SMS. Please provide the requested information and upload the required documents within maximum 5 business days to avoid closure of your application.

6. If a site survey is deemed necessary, you will receive a notification containing a transaction number to facilitate payment of the applicable fees.

7. Pay the related fees via the mRAK Smart App or payment machines at Customer Happiness Centres.

8.You will be notified of the application outcome via email and SMS.[MT1]

9. Receive the approved No Objection Certificate (NOC) together with the officially stamped proposal via RAK DIGITAL Portal.

How Much Will You Pay?

  • Free of charge, unless a surveyor is required (then fees may apply).


What Documents Do You Need?

Refer to the Infrastructure NOC Submission Guidelines below for a detailed list of the documents required based on the selected application subtype and stage.

Infrastructure NOC Submission Guidelines

What Terms and Limitations Apply?

Terms

  • You’ll need to register and create a Business Partner Account via the e-Services portal. For help, just reach out to the Customer Happiness Centre

Limitations and conditions

  • The issued No Objection Certificate (NOC) shall be valid for a period of six (6) months from the date of approval.

  • Applications for NOC renewal should be submitted at least two (2) weeks prior to the expiry date.

  • The holder shall comply with all notes, conditions, and requirements stated in the issued NOC certificate and approved drawings.

  • The issued NOC does not exempt the applicant from obtaining any other required approvals, permits, or clearances from relevant authorities.

  • All works and activities shall be carried out in accordance with the applicable laws, regulations, standards, and authority requirements.

  • Failure to comply with the conditions of the NOC, approved drawings, or applicable regulations may result in suspension, cancellation, or other regulatory action as deemed appropriate.

You can apply online through https://rakdigital.rak.ae/index.html?sap-language=en#/Lobby/MS16


FAQ

What is a No Objection Certificate (NOC)?

A No Objection Certificate is a formal document issued by the municipality confirming that a proposed project, development, or activity has been assessed for its potential impact on the ROW and existing and planned public infrastructure, transportation networks, and utilities, and that no objection exists to the proposal proceeding under the specified drawings, conditions and regulatory requirements.

Who can apply for a No Objection Certificate?

Governmental entities, Developers, Consultants and Contractors

How long does it take to get a No Objection Certificate?

The time it takes to receive a No Objection Certificate varies depending on the type of service requested.

Is there a fee for applying for a No Objection Certificate?

The application is free of charge unless a surveyor is required, in which case fees may apply.

What documents are needed to apply for a No Objection Certificate?

You need to submit an Infrastructure NOC Submission and follow the guidelines that outline all required documents based on the specific sub-service.

How do I apply for a No Objection Certificate?

What happens if my application is incomplete?

If your application does not meet the requirements, it will be rejected for insufficient data.

How will I be notified of the decision on my application?

You will be notified of the decision via email and text message.

What is the validity period of the issued NOC?

The validity period of the issued NOC is 6 months from the approval date.

Can I renew my No Objection Certificate?

Yes, you should renew your NOC at least 2 weeks before it expires.