ZP07 - Arrangement and Mobilization Permit

Prev Next

To help you get a head start on your construction project, we help you to obtain a permit to begin preparing your site even before securing the official building permit. This service is specifically designed for major commercial, investment, and government projects where time-sensitive pre-site preparation is critical.

With this permit, you're authorized to begin essential early-stage tasks such as installing a project board, setting up a temporary metal fence, excavation and foundation work, and bringing in cranes or heavy machinery—saving valuable time while your building permit is being processed.

How Long Will It Take? 6 working days

What Will You Get? Electronic Site Arrangement Permit

How Do You Apply?

  1. You can apply for this service through your consultant at https://rakdigital.rak.ae by using your UAE Pass and selecting “Arrangement and Mobilization Permit” to begin your application.

  2. Fill in the application form and upload all required documents.

  3. Pay the application fee.

  4. The referred engineer will review and approve the submitted documents and the inspection report.

  5. The licensed engineer will conduct a final audit and review of all documents, records, and the inspector’s report.

  6. Once approved, the permit will be issued electronically and available for download.

How Much Will You Pay?

  • Submission fee for all building types: AED 250


What Documents Do You Need?

  • Site plan : Affection plan and title deed (if available).

  • Trade License : A copy of the contractor’s Commercial Licence.

  • NOC for Site Service Clearance Certificate : No Objection Certificate (NOC) for Site Service Clearance Certificate – From relevant utility/service entities.

  • Assignment Letter – Site service clearance certificate, including NOC from Etihad Water and Electricity, Etisalat, Ras Al Khaimah Gas Company, and Public Works and Services Department (Wastewater Agency).


What Terms and Limitations Apply?

Terms :

  • Submit a new building permit request (ZP02) before this permit can be issued.​

Limitations

  • The permit is strictly for work conducted within the boundaries of the plot.

  • Validity: The permit is valid for 12 months from the date of issuance.


Services Link

You can apply online through https://rakdigital.rak.ae/index.html?sap-language=ar#/Lobby/ZP07


FAQ

What is the purpose of the electronic Site Arrangement Permit?

The electronic Site Arrangement Permit allows you to begin essential early-stage tasks for your construction project, such as site preparation, even before securing the official building permit.

How long does it take to obtain the Site Arrangement Permit?

It takes 6 working days to obtain the Site Arrangement Permit.

What tasks can I perform with the Site Arrangement Permit?

With the Site Arrangement Permit, you can install a project board, set up a temporary metal fence, conduct excavation and foundation work, and bring in cranes or heavy machinery.

What is the application fee for the Site Arrangement Permit?

The submission fee for all building types is AED 250.

What documents are required to apply for the Site Arrangement Permit?

You need a site plan, a copy of the contractor's trade license, a No Objection Certificate for Site Service Clearance, and an assignment letter for site service clearance.

Is the Site Arrangement Permit valid for a specific duration?

Yes, the Site Arrangement Permit is valid for 12 months from the date of issuance.

Can I start construction work outside the plot boundaries with this permit?

No, the permit is strictly for work conducted within the boundaries of the plot.

Do I need to submit a new building permit request before obtaining this permit?

Yes, you must submit a new building permit request (ZP02) before this permit can be issued.