Introduction
This user guide explains the applicable drawing standards and technical specifications, including file size, format, and other submission criteria, to help ensure that documents are prepared correctly for review.
It also provides clear instructions on how to submit and upload drawings through the system in response to case notifications.
Drawing Standards and Guidelines
Drawing Setup and Layout Standard
All drawings must be prepared and submitted in MODEL Space only.
Individual Files: One Sheet = One DWG file
.png?sv=2026-02-06&spr=https&st=2026-11-22T04%3A48%3A38Z&se=2026-11-22T05%3A03%3A38Z&sr=b&sp=r&sig=YlyztpPdKrrfD0OTIAluG08yg4lw%2FiqoK5T5t48WHzQ%3D)
Layout Space must not be used, and all viewports must be removed.
.png?sv=2026-02-06&spr=https&st=2026-11-22T04%3A48%3A38Z&se=2026-11-22T05%3A03%3A38Z&sr=b&sp=r&sig=WwHdusMZM2zFLeFUdbifIvjxZQrN6v050AB3Zm6h2eM%3D)
Do not place any objects outside the drawing frame.

Reserved Area: Keep the top-right corner of the drawing empty and free from any symbols, text, or data to allow space for Municipality stamps.

All layers must be ON and UNFROZEN
Titles: Do not use special characters in the Drawing Title or Job Number.
Data Entry
Use Block Attributes only. Double-click the block to enter the required information.
Important: Do not include any spaces in the attribute fields except client project and drawing title.

Mandatory Drawing Fields
The following information must be entered in the designated fields:
Case ID
Plot No.
Building No.
Sheet No.
Drawing Type
For Fence (FNC) Drawings: Enter the Fence ID (FNC No.) instead of the Building No.

Note: The Case ID and Building No. should be taken from the case details. Ensure that the number of buildings entered during case creation is correct
Draw Types Sample: Draw type is mandatory in all drawings.
.png?sv=2026-02-06&spr=https&st=2026-11-22T04%3A48%3A38Z&se=2026-11-22T05%3A03%3A38Z&sr=b&sp=r&sig=Wm7a%2Fa3956vbuFXq9UZ0Lpqckj7NhHIzIcewBJ%2BLCF0%3D)
Measurements (Architectural Only)
ARCH Floor Plan drawings must include a Measurement Block.
Enter numerical values only in the measurement fields.
Do not enter SQM, (m²) or any other text.
Area should be in square meters.

Floor Type and Numbering
Floor numbering must start from 01 and continue sequentially: 01–09, 10, 11, 12, and so on.
For two-digit floor numbers, do not add a leading zero (e.g., use 10, not 010).
When the floor type changes, restart the numbering sequence from 01.
.png?sv=2026-02-06&spr=https&st=2026-11-22T04%3A48%3A38Z&se=2026-11-22T05%3A03%3A38Z&sr=b&sp=r&sig=zVfU4Ybf1vPdanuYI1r4bQZHV%2Baxx8Wm%2FTHZ8IzJUgQ%3D)
Floor Type and Floor Number are mandatory for all Floor Plan drawings, except for:
- Barjeel (Mechanical, Plumbing, and Electrical).
- Structural (STRC).
- Elevations and Sections.
- Non-Floor Architectural Sheets.
- Drainage Drawings.
Floor Type and Numbering Reference
Floor Name | Floor type | Floor NO. |
Ground Floor | G | 01 |
First Floor | F | 01 |
Second Floor | F | 02 |
Third Floor | F | 03 |
Roof Floor | R | 01 |
Mezzanine Floor | M | 01 |
Basement Floor | B | 01 |
Basement Floor | B | 02 |
Exact Match: The file name must match the sheet number exactly.

Submission Rules
Continue numbering sequentially for multi-story buildings (02,03,04…). For floors 10 and above, use 10, 11, 12… (do not use 010, 011, 012).
Upload each floor drawing separately.
Do not combine Ground Floor and First floor.
Remove Floor number and floor type from Part Plans floor drawings.
Sheet Numbering Requirements
General Rules:
Sheet numbers must be unique.
Do not repeat sheet numbers even if the building number is different.
Sheet numbering must continue sequentially.
Exception Cases:
Sheet number is not required in the EWE drawing.
Sheet Prefixes by Discipline
Discipline | Prefix | Example |
Architectural | A | A001 |
Structural | S | S001 |
Civil Défense | C | C001 |
Drainage | D | D001 |
Etisalat | E | E001 |
Electrical (GBR) | ME | ME001 |
Mechanical (GBR) | M | M001 |
Plumbing (GBR) | MP | MP001 |
Discipline Codes
Discipline | Drawing Type |
Architectural | ARCH |
Structural | STRC |
Drainage | DRNG |
Electrical (GBR) | ELEC |
Civil Defense | CIVL |
Etisalat | ETIS |
Plumbing (GBR) | PLMP |
Mechanical (GBR) | MECH |
Municipality Frame
Floor Drawings Submission Rules
Each floor drawing must be uploaded in a separate sheet.
Do not combine the Ground Floor and First Floor on the same sheet.
Other drawing may be combined on the same sheet if applicable
EWE Drawings Rules
EWE-related drawings (Electrical & Water) must be submitted in PDF format only.
Civil Defense Drawing Rules (CD)
Floor Type & Floor Number (CD)
Do not repeat Floor Type & Floor Number for the same building.
Only one floor type drawing is allowed per floor for each building.
Keep the Floor Type & Floor Number only in CD-FLS drawings.
File Naming (CD)
Do not use special characters.
keep file names as short as possible
Note: Verify floor assignment and sheet uniqueness before submission.
Drainage Drawing Rules (DRNG)
Floor Type & Floor Number (DRNG)
Floor type & Floor Number are not required for Drainage drawings
Additional Rules (DRNG)
Remove spaces before title block values.
Leave unused field completely blank.
Barjeel Drawing Rules (GBR)
Draw type of barjeel (MECH) (PLMP)
Floor Type and Floor Number (GBR)
Floor Type & Floor Number are not required for Barjeel drawings.
Additional Rules (GBR)
Keep unused fields completely blank
Etisalat Drawing Rules (ETIS)
Checklist Before Submission (ETIS)
Check all required sheets are included.
Floor Type & Floor Number (ETIS)
Required only in floor Plans.
Remove from Part Plans.
Additional Rules (ETIS)
Remove spaces from floor type.
Keep unused fields blank.
Etisalat drawing is required for basement and roof floor.
File Naming Requirements
File name must include sheet NO. and drawing title and should match exactly with the details of the drawing.
Forbidden characters: ( - _ \ / @ # & spaces ).
Short Length
Allowed: A001.ground floor, GF01.dwg, S001.dwg.
Not Allowed: A-001.dwg (hyphen), Ground_Floor.dwg(underscore), ARCH#01.dwg
Access the Portal
Visit the RAK Digital Portal: https://rakdigital.rak.ae/
Select Your Preferred Language.
Click "Login" and sign in using your UAE PASS credentials.

After logging in, click the “Home” icon to view all services that require action from your side.

Drawing Upload
First Drawing Upload
After completing the initial fee payment, you will be required to upload the requested documents. The request status will appear as “Pending with Customer.”
Click the “Upload” button to proceed.

After clicking the Upload button, the Upload screen will display all drawings required for submission.
Review the available notifications for each discipline. Each discipline will have a separate notification for uploading its required drawings.
Select the relevant notification and upload the drawings under the corresponding section.
For Municipality drawings, select the notification titled “Upload Drawings.”
For other disciplines, refer to the description and notification number to identify the correct notification before uploading the drawings.
.png?sv=2026-02-06&spr=https&st=2026-11-22T04%3A48%3A38Z&se=2026-11-22T05%3A03%3A38Z&sr=b&sp=r&sig=7y4T1c0QhTLxZ1taNtut70W8iRGleyh0aU3SPlDl2ZU%3D)
Expand the relevant notification to view the upload section.
Click the Select a File Icon “
” to browse your device and select the required drawing.You can now upload multiple documents at once as shown below.
Once all required drawings are uploaded, click Done to proceed.
.png?sv=2026-02-06&spr=https&st=2026-11-22T04%3A48%3A38Z&se=2026-11-22T05%3A03%3A38Z&sr=b&sp=r&sig=UO8%2Bs58JJGEcyigN7v9cgtM3RRgC5GZnHrP1iHNbcXo%3D)
After uploading all required drawings, the request will be reviewed. Once the review is completed, the request status will be updated to “In Progress.”

Resubmitting Rejected Drawings
If any of the submitted drawings are rejected during the review, the request status will change to “Pending with Customer.”
Click the “Upload” button to view the required action and resubmit the drawings.

After clicking the Upload button, the Upload screen will display the drawings that require resubmission.
Review the listed notifications to identify which drawings require action.

Expand the relevant notification to review the department notes and identify the drawings that require resubmission.
Upload the updated drawings by selecting the Select a File Icon “
” as specified in the department notes.You can now upload multiple documents at once as shown below.
Once all required drawings have been uploaded, click Submit to complete the resubmission.
Repeat the same steps for all notifications that require action.